Inserted projects are calculated like summary tasks
- Policy ID
- L_PjInsertedProjects
- Scope
- User Configuration
- Supported on
- At least Windows Server 2008 R2 or Windows 7
- Source
- Microsoft 365 Apps / Office Administrative Templates (version 5568.1000)
- Category
- Microsoft Project 2016 › Project Options › Calculation › Calculation options for 'Project1'
Description
Specifies that a single critical path is calculated throughout the master project, by treating inserted projects as summary tasks in the master project.
If you enable this setting, the critical path is calculated by treating inserted projects as summary tasks.
If you disable or do not configure this setting, the user's default setting is used.
Registry
UserHKEY_CURRENT_USER
- inserted projects are calculated like summary tasksREG_DWORD