Updating task status updates resource status

Policy ID
L_PjUpdatingTask
Scope
User Configuration
Supported on
At least Windows Server 2008 R2 or Windows 7
Source
Microsoft 365 Apps / Office Administrative Templates (version 5568.1000)
Category
Microsoft Project 2016 › Project Options › Calculation › Calculation options for 'Project1'

Description

Automatically updates resource status, such as actual and remaining work and cost, whenever you update task status, such as percent complete, actual duration, or remaining duration.

If you enable this setting, task status updates are automatically applied to resources.

If you disable or do not configure this setting, the user's default setting is used.

Registry

Other policies in the same category