Set default start date for new tasks

Bu dilde resmi metin yok (İngilizce özgün metin gösteriliyor)

İlke Kimliği
L_SetDefaultStartDateForNewTasks
Kapsam
Kullanıcı Yapılandırması
Desteklenen işletim sistemleri
En az Windows Server 2008 R2 veya Windows 7
Kaynak
Microsoft 365 Apps / Office Administrative Templates (sürüm 5568.1000)
Kategori
Microsoft Project 2016 › Project Options › Schedule › Scheduling options for 'Project1'

Açıklama

This policy setting specifies the default start date for new tasks as they are entered in the current project. For projects scheduled from the start date, the options are "Start on Project Start Date" and "Start on Current Date." For projects scheduled from the finish date, the options are "Finish on Project Finish Date" and "Start on Current Date."

If you enable or do not configure this policy setting, new tasks will start on the project start date.

If you disable this policy setting, new tasks will not start on the project start date.

Kayıt defteri

KullanıcıHKEY_CURRENT_USER
  • new tasks start on current dateREG_DWORD

Aynı kategorideki diğer ilkeler