Set default start date for new tasks
Brak oficjalnego tekstu w tym języku (wyświetlono oryginał angielski)
- Identyfikator zasady
- L_SetDefaultStartDateForNewTasks
- Zakres
- Konfiguracja użytkownika
- Obsługiwane w systemach
- System Windows Server 2008 R2 lub nowszy albo system Windows 7
- Źródło
- Microsoft 365 Apps / Office Administrative Templates (wersja 5568.1000)
- Kategoria
- Microsoft Project 2016 › Project Options › Schedule › Scheduling options for 'Project1'
Opis
This policy setting specifies the default start date for new tasks as they are entered in the current project. For projects scheduled from the start date, the options are "Start on Project Start Date" and "Start on Current Date." For projects scheduled from the finish date, the options are "Finish on Project Finish Date" and "Start on Current Date."
If you enable or do not configure this policy setting, new tasks will start on the project start date.
If you disable this policy setting, new tasks will not start on the project start date.
Rejestr
UżytkownikHKEY_CURRENT_USER
- new tasks start on current dateREG_DWORD