Edits to total task % complete will be spread to the status date: kayıt defteri değeri edits to total task %complete will be spread to the status dateKullanıcıHKCU\software\policies\microsoft\office\16.0\ms project\options\calculation
Bu dilde resmi metin yok (İngilizce özgün metin gösteriliyor)
- İlke Kimliği
- L_PjEditstoTotalTask
- Kapsam
- Kullanıcı Yapılandırması
- Desteklenen işletim sistemleri
- En az Windows Server 2008 R2 veya Windows 7
- Kaynak
- Microsoft 365 Apps / Office Administrative Templates (sürüm 5568.1000)
- Kategori
- Microsoft Project 2016 › Project Options › Calculation › Calculation options for 'Project1'
Kayıt defteri
edits to total task %complete will be spread to the status date
REG_DWORDKullanıcı- Etkin değeri
- 1
- Devre dışı değeri
- 0
.reg · CMD · PowerShell ile uygula
.reg
Windows Registry Editor Version 5.00 [HKEY_CURRENT_USER\software\policies\microsoft\office\16.0\ms project\options\calculation] ; Seçenekler (yalnızca birini kullanın) ; Etkin "edits to total task %complete will be spread to the status date"=dword:00000001 ; Devre Dışı "edits to total task %complete will be spread to the status date"=dword:00000000
CMD
:: Seçenekler (yalnızca birini kullanın) :: Etkin reg add "HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation" /v "edits to total task %complete will be spread to the status date" /t REG_DWORD /d 1 /f :: Devre Dışı reg add "HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation" /v "edits to total task %complete will be spread to the status date" /t REG_DWORD /d 0 /f
PowerShell
# Ortak: anahtarı oluştur New-Item -Path 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation' -Force | Out-Null # Seçenekler (yalnızca birini kullanın) # Etkin New-ItemProperty -Path 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation' -Name 'edits to total task %complete will be spread to the status date' -PropertyType DWord -Value 1 -Force | Out-Null # Devre Dışı New-ItemProperty -Path 'HKCU:\software\policies\microsoft\office\16.0\ms project\options\calculation' -Name 'edits to total task %complete will be spread to the status date' -PropertyType DWord -Value 0 -Force | Out-Null