Actual costs are always calculated by Microsoft Project
- Policy ID
- L_PjActualCostsCalc
- Scope
- User Configuration
- Supported on
- At least Windows Server 2008 R2 or Windows 7
- Source
- Microsoft 365 Apps / Office Administrative Templates (version 5568.1000)
- Category
- Microsoft Project 2016 › Project Options › Calculation › Calculation options for 'Project1'
Description
Specifies that Project calculates actual costs automatically, based upon resource rates, per-use resource costs, and fixed task costs.
If you enable this setting, Project will automatically calculate actual costs.
If you disable or do not configure this setting, the user's default setting is used.
Registry
UserHKEY_CURRENT_USER
- actual costs are always calculated by microsoft office projectREG_DWORD