Split in-progress tasks
- Policy ID
- L_PjSplitinProgressTasks
- Scope
- User Configuration
- Supported on
- At least Windows Server 2008 R2 or Windows 7
- Source
- Microsoft 365 Apps / Office Administrative Templates (version 5568.1000)
- Category
- Microsoft Project 2016 › Project Options › Schedule › Scheduling options for 'Project1'
Description
Allows rescheduling of remaining duration and work when a task slips or reports progress ahead of schedule.
If you enable this setting, the remaining duration and work will be rescheduled if a task slips or reports progress ahead of schedule.
If you disable or do not configure this setting, the user's default setting is used.
Registry
UserHKEY_CURRENT_USER
- auto split tasksREG_DWORD